The Details
Workers
0
Waterproofers
0
Working Hours
0
Preliminary steps to take before choosing waterproofing materials and system. 1. Clean the substrate;
2. Examine the surfaces to be waterproofed;
prepare the surfaces;
3.check and renovate the joints and the wells;
4.proceed to the waterproofing of joints and drains.
Scope of work completed on this project
- Removed and replaced cracked and broken roof tiles.
- No barge boards to prevent water penetration.
- Install and counter flash onto roof tiles.
- Due to roof tiles being laid virtually flat, this is allowing water to stream into the Kitchen.
- Removed tiles and lay down 23mm ply boards onto rafters.
- Heat fused a 4mm torch-on onto ply boards and allow 500mm under tiles.
- Counter flashed the system onto garage roof to prevent return waterflow.
- Repaired all gutter joints.
- Replaced the missing corrugated polycarbonate roof sheets.
Job Progress
Work Completed 100%
Lets Take a Closer Look
The Testimonial
About The Project
- Date:27th February 2018
- Category: Tiled Roofs
- Likes: 0 like
- Share: